UNIT-4 Breach and Remedies
Table of Contents
Question-Define breach of contract under Section 73. Discuss the remedies available for breach of contract
Definition: Breach of Contract under Section 73 of the Indian Contract Act, 1872
Section 73 of the Indian Contract Act, 1872 deals with compensation for loss or damage caused by breach of contract.

Section 73 – Legal Provision:
“When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it.”
It further provides that remote and indirect loss or damage sustained by reason of the breach is not recoverable.
Key Points:
- Breach: Failure or refusal to perform a contractual obligation.
- Entitlement: The aggrieved party can claim compensation for losses.
- Types of Losses Covered:
- Loss naturally arising from the breach (direct loss).
- Loss that the parties could foresee at the time of contract (consequential loss).
Remedies for Breach of Contract under Indian Law
When a contract is breached, several remedies are available to the aggrieved party. These include:
1. Damages (Compensation)
Under Section 73, damages are the most common remedy. There are several types of damages:
a. General or Ordinary Damages:
Compensation for the loss that arises naturally due to the breach.
Case Law: Hadley v. Baxendale (1854)
- Principle: The defendant is liable for those consequences that arise naturally or that were foreseeable by both parties at the time of the contract.
- Influence: This case is the foundation of Section 73 in Indian law.
b. Special Damages:
Losses that are not natural but arise due to special circumstances, which must be communicated to the other party.
c. Exemplary or Punitive Damages:
Awarded rarely, to punish the defaulting party (usually in tort, not contract law).
d. Nominal Damages:
A small amount awarded where a legal wrong occurred but no real damage was suffered.
2. Specific Performance
Under the Specific Relief Act, 1963, courts may order the party in breach to perform their part of the contract.
Usually granted when:
- Damages are not an adequate remedy.
- Subject matter is unique (e.g., sale of land).
Case: K.S. Vidyanadam v. Vairavan (1997)
The Supreme Court ruled that specific performance is discretionary and should be granted only when equitable.
3. Injunction
A court order restraining a party from doing something which breaches the contract (prohibitory injunction) or compelling them to do a specific act (mandatory injunction).
Example: In employment or non-compete agreements.
4. Quantum Meruit
If a contract is discharged or breached mid-way, a party may claim payment “as much as is deserved” for the part already performed.
Case: Craven-Ellis v. Canons Ltd. (1936)
Recognized that one can recover payment for services rendered when the contract is not fully executed.
5. Rescission of Contract
The aggrieved party may cancel the contract and refuse to perform their part. Available under Sections 39 and 75 of the Contract Act.
Conclusion:
Section 73 is a crucial provision ensuring fair compensation in case of breach. The primary aim is to put the aggrieved party in the same position as if the contract had been performed.
Summary Table:
Remedy | Legal Basis | Example/Case Law |
---|---|---|
Damages (Section 73) | Indian Contract Act, 1872 | Hadley v. Baxendale |
Specific Performance | Specific Relief Act, 1963 | K.S. Vidyanadam v. Vairavan |
Injunction | Specific Relief Act | Niranjan Shankar Golikari v. Century Spinning |
Quantum Meruit | Common Law Principle | Craven-Ellis v. Canons Ltd. |
Rescission | Section 39 & 75, Contract Act | Based on non-performance or repudiation |
Question- Explain the concept of specific performance under the Specific Relief Act, 1963 (Sections 9-14). When can it be granted?
โ Concept of Specific Performance under the Specific Relief Act, 1963 (Sections 9โ14)
Specific Performance is an equitable remedy that directs a party to perform their obligations under a contract, rather than simply pay damages for non-performance.

Under the Specific Relief Act, 1963, Sections 9 to 14 outline when specific performance can be claimed, granted, or refused.
๐ What is Specific Performance?
Specific performance is a court-ordered remedy where the defaulting party must perform the contract as agreed.
It is typically used when:
- Damages are inadequate, and
- The subject matter is unique (e.g., immovable property).
๐ Relevant Sections: Overview
Section | Provision |
---|---|
Section 9 | Defenses in a suit for specific performance |
Section 10 | Cases in which specific performance is enforceable |
Section 11 | Contracts made by trustees (may be specifically enforced) |
Section 12 | Specific performance of part of contract |
Section 13 | Rights of purchaser or lessee against a person with no title |
Section 14 | Contracts that cannot be specifically enforced |
๐ Section 9: Defenses in a Suit for Specific Performance
- A party suing for specific performance must be ready and willing to perform their part.
- All defenses available in contract law (e.g., fraud, misrepresentation, impossibility) are available.
๐ Section 10: Cases Where Specific Performance Can Be Enforced
Specific performance may be ordered when:
- There is no standard for ascertaining actual damage, or
- Compensation in money is not an adequate relief
โ Examples:
- Sale of immovable property (land, building, etc.)
- Rare or unique goods, artworks, heirlooms
๐ Section 11: Contracts by Trustees
- A trustee may be compelled to perform contracts entered into within the scope of their authority.
๐ Section 12: Part Performance
Generally, partial specific performance is not allowed, unless:
Allowed if:
- The part unperformed is small and can be compensated in money.
- The contract is divisible.
- The plaintiff is willing to accept partial performance with compensation.
Case Law: Surya Narain Upadhyaya v. Ram Roop Pandey (1994)
- Held that partial specific performance may be allowed where the non-performance part is minor.
๐ Section 13: Rights Against a Person with No Title
- If a person contracts to sell property they donโt own but later acquire ownership, the buyer can enforce the contract.
๐ Section 14: Contracts Not Specifically Enforceable
Specific performance shall not be granted in the following cases:
- Substituted performance has already been obtained under Section 20.
- Contracts involving personal skill or volition (e.g., painting, acting).
- Contracts that are determinable by nature.
- Contracts that involve continuous duty and are not supervised by the court.
- Where monetary compensation is an adequate remedy.
Example: A contract to perform in a musical show cannot be specifically enforced.
Case Law: K.S. Vidyanadam v. Vairavan (1997)
- Specific performance is discretionary and not automatic. Delay or inequity can bar the relief.
โ When Can Specific Performance Be Granted?
โ๏ธ Conditions:
- Valid, enforceable contract exists.
- Plaintiff is ready and willing to perform their obligations.
- Subject matter is unique, or damages are inadequate.
- The contract is fair, not opposed to public policy.
โ When It Cannot Be Granted:
- Contracts of personal nature or skill.
- Contracts that are vague, uncertain, or incomplete.
- Contracts where adequate monetary damages are possible.
- If the plaintiff has breached or delayed significantly.
๐ Conclusion:
Specific performance is an equitable, discretionary remedy granted by courts to ensure fair enforcement of contracts, especially where monetary damages fall short. Sections 9 to 14 of the Specific Relief Act, 1963 provide a structured approach for its application.
Question- Discuss the rules regarding damages for breach of contract under Sections 73-75. Refer to Syed Dastagir v. J.R. Gopalakrishna Setty.
Sections 73โ75: Damages for Breach of Contract
๐น Section 73 โ Compensation for Loss or Damage caused by Breach of Contract
This section deals with awarding compensatory damages to the aggrieved party when a contract is breached.
Text Summary:
When a contract is broken, the aggrieved party is entitled to compensation for:
- Loss or damageย naturally arising in the usual courseย of events, or
- Loss which the partiesย knew to be likely to resultย from the breach at the time of entering the contract.
๐ซ Remote or indirect losses are not compensable.
๐น Section 74 โ Compensation for Breach of Contract where Penalty is Stipulated
This section covers liquidated damages and penalties.
If a contract mentions a sum to be paid or penalty on breach, the aggrieved party is entitled to reasonable compensation, not exceeding the stipulated amount.
๐ก No need to prove actual lossโbut compensation must be reasonable, not punitive.
Case Reference: Fateh Chand v. Balkishan Das (1964)
- The Supreme Court held that the court must determineย reasonable compensation, even if a specific amount is mentioned.
๐น Section 75 โ Compensation to Party Rightfully Rescinding the Contract
A party who lawfully rescinds a contract is entitled to compensation for damages sustained due to non-fulfilment of the contract.
๐ Key Rules from Sections 73โ75
Rule | Explanation |
---|---|
Damages should compensate actual loss | Not meant to punish but to restore the injured party to the position they were in. |
Damages must be foreseeable | Only losses that are natural or known at the time of contract are compensable. |
Liquidated damages โ penalty | Compensation is awarded up to the pre-agreed sum if reasonable. |
No double compensation | Compensation is only awarded once for a single cause of loss. |
Duty to mitigate damages | The injured party must try to reduce or avoid losses after breach. |
โ๏ธ Case Law: Syed Dastagir v. J.R. Gopalakrishna Setty, (1999) 6 SCC 337
๐ Facts:
- A lease agreement was signed betweenย Syed Dastagir (landlord)ย andย J.R. Gopalakrishna Setty (tenant).
- The tenant failed to comply with lease terms andย unilaterally refused possession.
- The landlord sued for damages due to breach.
๐ Legal Issue:
Was the landlord entitled to damages for breach of contract under Section 73?
๐ Held:
- The Supreme Court held thatย refusal to accept possession amounted to breach.
- Damages must be assessed based onย actual lossย suffered due to refusal.
- The court reiterated thatย Section 73 covers both natural and foreseeable loss, and thatย damages should be fair and reasonable.
๐ Significance:
- Reaffirmed thatย damages are compensatory, not penal.
- Highlights importance of provingย actual or probable loss.
- Reinforcesย Section 73 principlesย in landlord-tenant and property-related contracts.
๐ Conclusion
Sections 73โ75 of the Indian Contract Act, 1872 provide a comprehensive framework for determining compensationin case of a breach of contract. The rules ensure that:
- Onlyย reasonable and foreseeableย losses are compensated,
- Stipulated penaltiesย are subject to judicial scrutiny,
- And the injured party must act responsibly toย mitigate their losses.
The case of Syed Dastagir v. J.R. Gopalakrishna Setty is a key precedent that illustrates the application of Section 73to real estate lease contracts and emphasizes fair compensation based on actual loss.
Question-Explain the powers of the court in granting specific performance under Sections 20-24.
๐ Specific Relief Act, 1963 โ Sections 20 to 24: Powers of the Court in Granting Specific Performance
The sections deal with how courts exercise discretionary powers to grant, refuse, or guide specific performance.
๐น Section 20 โ Substituted Performance of Contract (Inserted in 2018)
- If one party breaches the contract, the aggrieved party may get the contract performed by a third party or own agency and recover the expenses from the breaching party.
- In such cases, the aggrieved party cannot claim specific performance.
โ ๏ธ However, prior notice (30 days) must be given to the defaulting party.
๐น Section 20A โ No Specific Performance in Infrastructure Contracts (New)
- Courts shall not grant injunctions in disputes involving infrastructure projects if such injunctions would delay or hinder progress.
- Applies to sectors like transport, energy, water, etc.
๐น Section 20B โ Special Courts for Infrastructure Projects (New)
- Designated Special Courts will hear matters involving infrastructure contracts.
๐น Section 20C โ Expeditious Disposal of Suits (New)
- Suits for specific performance should ideally be disposed of within 12 months from the date of service of summons (with a 6-month extension possible).
๐น Section 21 โ Power to Award Compensation in Certain Cases
- The court may grant compensation along with or in substitution of specific performance.
- The plaintiff must claim compensation in the plaint, but the court may permit amendment later.
โ Useful when part of the contract is performed or specific performance becomes impossible.
๐น Section 22 โ Power to Grant Relief for Possession, Partition, Refund
- In suits for specific performance of contracts involving immovable property, the plaintiff can also seek:
- Possession or partition, or
- Refund of earnest money or deposit if specific performance is not granted.
Relief must be claimed in the plaint, though the court may allow amendments later.
๐น Section 23 โ Liquidation of Damages Not a Bar to Specific Performance
- If the contract mentions liquidated damages, the aggrieved party can still seek specific performance, unless the party has accepted compensation in full and final settlement.
๐ก Example: If the contract says โโน1 lakh will be paid on breach,โ it doesnโt bar the court from enforcing the contract specificallyโunless the aggrieved party has already accepted that money as final.
๐น Section 24 โ Bar on Suit for Compensation for Breach After Dismissal of Specific Performance Suit
- If a court refuses specific performance, the plaintiff cannot file a separate suit for compensation.
- However, if the plaintiff has claimed both specific performance and compensation, and only specific performance is refused, the court may award compensation in the same suit.
โ๏ธ Summary of Powers of the Court
Section | Power/Provision |
---|---|
20 | Allows substituted performance, bars specific performance in such cases |
20A | Restriction on injunctions in infrastructure projects |
20B | Establishment of Special Courts for speedy disposal |
20C | Court must attempt to dispose suits in 12 months |
21 | Power to award compensation with or instead of specific performance |
22 | Power to grant possession, partition, or refund in immovable property contracts |
23 | Specific performance allowed despite penalty/compensation clause |
24 | Prevents filing new suit for damages after dismissal of suit for specific performance |
๐ง Key Takeaways
- Specific performance is no longer discretionary post-2018 in many casesโcourts shall enforce it, unless exceptions apply.
- Courts have wide powers to award alternative or additional relief like possession, partition, refund, and damages.
- New provisions emphasize efficiency, especially for infrastructure projects.
Question -Discuss the provisions related to rectification and cancellation of instruments under Sections 26-33
๐ Chapter III & IV of Specific Relief Act, 1963
- Sections 26 to 30 โ ๐ Rectification of Instruments
- Sections 31 to 33 โ ๐ Cancellation of Instruments
These provisions give civil courts the power to correct or cancel contracts and documents (instruments) in certain circumstances to ensure fairness and justice.
๐ง I. Rectification of Instruments (Sections 26โ30)
โ What is Rectification?
Rectification means correcting a written document so it reflects the true intention of the parties, where a mistake or fraud caused it to differ from the agreement.
๐น Section 26 โ When Instrument May Be Rectified
โ๏ธ Key Conditions:
- Mistake or fraud must be proved.
- The mistake must be mutualโboth parties misunderstood.
- It must relate to a written instrument, not oral agreements.
๐จโโ๏ธ Relief:
- The court may rectify the instrument on an application by the party seeking it.
- Can be claimed as:
- A main suit, or
- A relief in an existing suit (e.g., for specific performance).
โ ๏ธ Limitation: Must be claimed in the plaint, or amendment must be allowed.
Example: A sale deed wrongly mentions 50 square meters instead of 500 square meters due to mutual error.
๐น Section 27 โ Presumption as to Intent of Parties
If an instrument was meant to carry out a previous contract, the court presumes that the instrument was intended to be in conformity with the original agreement, unless proved otherwise.
โ Useful in specific performance suits involving rectification claims.
๐น Section 28 โ Effect of Rectification
Once rectified:
- The document has the same legal effect as if it had originally been executed in its rectified form.
- Binds both the parties and third parties who have notice of rectification.
๐น Section 29 โ Alternative Prayer for Rectification
The plaintiff may:
- Claim specific performance, and
- As an alternative, seek rectification of the instrument if required.
This ensures flexibility and avoids multiplicity of suits.
๐น Section 30 โ Presumption Against Rectification
The court shall not grant rectification if:
- The party seeking rectification was grossly negligent.
- The mistake is not mutual.
โ ๏ธ One-sided mistakes or negligence bar the relief.
๐๏ธ II. Cancellation of Instruments (Sections 31โ33)
โ What is Cancellation?
Cancellation means legally nullifying a written instrument (like a deed, agreement, or contract) if it is void, voidable, or harmful to a party.
๐น Section 31 โ When Cancellation May Be Ordered
โ๏ธ Conditions:
- The instrument is void or voidable against the applicant, and
- The instrument, if left outstanding, may cause serious injury to the applicant.
The court may order cancellation either wholly or partly.
Example: A forged sale deed may be cancelled by the rightful landowner.
๐น Section 32 โ Power to Require Delivery of Cancelled Instruments
- The court may direct the party whose document is cancelled to deliver it to be destroyed or filed with the court.
- Ensures the invalid document cannot be misused.
๐น Section 33 โ Relief for Executed Persons or Sureties
- If a document is cancelled, any person who executed it or acted as a surety or representative may also claim relief from obligations under it.
โ๏ธ Comparison Table: Rectification vs. Cancellation
Aspect | Rectification (Sec. 26โ30) | Cancellation (Sec. 31โ33) |
---|---|---|
Nature | Correction of document | Annulment of document |
Reason | Mutual mistake or fraud | Document is void/voidable and causes injury |
Relief granted | Corrected instrument reflects original intent | Document made ineffective in law |
Who can apply | Any party to the instrument | Person affected by instrument |
Result | Modified version remains valid | Document is legally cancelled |
๐ง Key Takeaways:
- Rectification applies when there’s a mistake in expressing the contract, but both parties intended something else.
- Cancellation applies when a document is invalid or harmful and should no longer have legal effect.
- Courts exercise these powers to uphold fairness, prevent fraud, and correct genuine errors in legal documentation.
Question-What are injunctions under Sections 36-42 of the Specific Relief Act? Differentiate between temporary and permanent injunctions.
๐ Injunctions (Sections 36โ42) โ Specific Relief Act, 1963
An injunction is a judicial order requiring a person to do or refrain from doing a particular act.
๐งพ Section-wise Overview
๐น Section 36 โ Preventive Relief
- Preventive relief is granted by injunction, which may be:
- Temporary, or
- Perpetual (Permanent)
๐น Section 37 โ Types of Injunctions
1. Temporary Injunctions
- Granted during a suit to maintain the status quo until the case is decided.
- Regulated by Order XXXIX, Rules 1 & 2 of the Code of Civil Procedure, 1908.
- Passed by civil courts based on urgency or risk of irreparable injury.
๐ Example: Stopping a builder from constructing on disputed land until title is settled.
2. Perpetual Injunctions (Permanent Injunctions)
- Granted by the final decree in a suit.
- Permanently restrains a party from doing something that would:
- Infringe on the plaintiffโs rights,
- Violate a contract,
- Cause irreparable harm.
โ Example: Permanently prohibiting a factory from discharging pollutants into a river.
๐น Section 38 โ Perpetual Injunctions (When Granted)
The court may grant a perpetual injunction to:
- Prevent breach of an obligation (whether arising out of contract or otherwise),
- Protect the plaintiffโs legal or equitable interest in property or right.
โ Even negative covenants in contracts (e.g., not to compete) may be enforced by injunction.
๐น Section 39 โ Mandatory Injunction
- A court may compel a party to perform a specific act to prevent breach of an obligation.
- It is a positive order (unlike most injunctions which are prohibitory).
๐ ๏ธ Example: Order to remove an encroachment on someone’s land.
๐น Section 40 โ Damages in Lieu of or in Addition to Injunction
- Plaintiff may claim damages either:
- Along with an injunction, or
- Instead of an injunction (if not granted).
๐ Must be claimed in the suit, or the court may allow an amendment.
๐น Section 41 โ When Injunction Cannot Be Granted
Injunctions cannot be granted in the following situations:
- To prevent judicial proceedings,
- To restrain actions already decided by a competent court,
- To stop people from legally exercising a statutory duty,
- To prevent breach of contract that cannot be specifically enforced,
- To stop someone from filing a suit in the same or different court,
- To enforce negative covenants in contracts not legally valid,
- If adequate relief can be obtained through damages,
- If it would cause greater hardship to the defendant than relief to plaintiff.
๐น Section 42 โ Injunction to Perform Negative Agreement
- If a contract includes a negative covenant (e.g., not to work for a competitor), the court may grant an injunction to enforce it.
- Applicable even if the contract is not specifically enforceable.
๐ Example: An actor agreeing not to work with other producers for a fixed time can be restrained if they violate the agreement.
๐ Difference Between Temporary and Permanent Injunctions
Feature | Temporary Injunction | Permanent Injunction |
---|---|---|
Section | Governed under Section 37(1) + CPC Order 39 | Section 37(2), 38 |
Nature | Interim relief | Final relief |
Duration | Till the final decision of the case | Indefinite (permanent), granted by final decree |
When Granted | At any stage of the suit | At conclusion of the suit |
Purpose | To preserve status quo | To prevent or stop a continuing/future legal injury |
Revocable? | Yes, can be modified or vacated | No, unless appealed or set aside |
Requirement of Suit? | No separate suit required | Requires full-fledged suit under civil procedure |
โ๏ธ Important Case Law
- Dalpat Kumar v. Prahlad Singh (1992)
- Court laid down criteria for temporary injunctions:
- Prima facie case,
- Balance of convenience,
- Irreparable injury.
- Gujarat Bottling Co. v. Coca Cola Co. (1995)
- Negative stipulations in contracts can be enforced by injunction.
- Cotton Corporation v. United Industrial Bank (1983)
- Court cannot issue injunctions to restrain lawful initiation of legal proceedings.
๐ง Conclusion
Sections 36 to 42 of the Specific Relief Act empower courts to:
- Prevent harm by restraining wrongful acts (injunctions),
- Compel action to undo or prevent violation (mandatory injunction),
- Ensure that justice is served proactively and not merely through compensation.
Question-Critically analyze the role of liquidated damages and penalty clauses in contracts.
Certainly! Here’s a critical analysis of the role of liquidated damages and penalty clauses in contracts under Indian law, with references to relevant sections, principles, and case law:
๐ 1. Introduction to Liquidated Damages and Penalty Clauses
In commercial contracts, parties often include clauses specifying a predetermined amount payable on breach. These can be either:
- Liquidated damages โ a genuine pre-estimate of loss,
- Penalty clauses โ an amount meant to deter breach, often excessive.
๐ Relevant Provision:
Section 74 of the Indian Contract Act, 1872 governs both.
โ๏ธ 2. Legal Provision: Section 74 โ Compensation for Breach of Contract Where Penalty is Stipulated
โWhen a contract has been broken, if a sum is named in the contract as the amount to be paid in case of breachโฆ the party complaining of the breach is entitledโฆ to reasonable compensation not exceeding the amount so namedโฆโ
๐ก Key Features:
- The injured party is entitled to reasonable compensation, not automatically the full amount specified.
- No need to prove actual loss, but courts will examine whether loss is likely to have occurred.
- The clause may be labelled โpenaltyโ or โliquidated damagesโ โ courts examine substance over form.
๐ 3. Difference Between Liquidated Damages and Penalty
Feature | Liquidated Damages | Penalty Clause |
---|---|---|
Purpose | To estimate likely loss in advance | To deter breach by threat of punishment |
Amount | Reasonable and proportionate | Excessive or extravagant |
Enforceability | Enforceable up to the amount as reasonable | Not enforceable beyond reasonable compensation |
Assessed by Court? | Court may still reduce based on facts | Court will almost always assess/reduce amount |
๐ 4. Judicial Approach in India
Indian courts do not strictly follow the English law distinction between liquidated damages and penalty. Instead, they adopt a balanced, equitable approach under Section 74.
๐น Leading Case: Fateh Chand v. Balkishan Dass (AIR 1963 SC 1405)
The Supreme Court held:
- The party is entitled only to reasonable compensation, not necessarily the entire sum.
- Proof of actual loss is not essential, but compensation must be justifiable.
๐น ONGC v. Saw Pipes Ltd. (2003) 5 SCC 705
Expanded the principle:
- If loss is difficult to prove, and the stipulated amount is a genuine pre-estimate, it may be awarded in full.
- Introduced the test of reasonableness and proportionality.
- Emphasized commercial certainty in large infrastructure contracts.
๐น Kailash Nath Associates v. DDA (2015) 4 SCC 136
Reiterated:
- No compensation if no breach occurred, or if no loss was caused.
- Section 74 does not allow unjust enrichment.
๐ 5. Critical Analysis: Benefits vs. Challenges
โ Merits / Importance:
- Predictability & Certainty: Provides clarity in commercial arrangements.
- Saves Litigation Time: Avoids the need to prove actual damage in every case.
- Risk Allocation: Helps parties manage risk effectively.
- Encourages Performance: Acts as a deterrent against casual breaches.
โ Limitations / Criticisms:
- May Lead to Unjust Enrichment: Especially when no loss is suffered.
- Judicial Discretion Reduces Certainty: Courts often reduce stipulated amounts, leading to unpredictability.
- Deterrence vs. Compensation Conflict: Penalty clauses aimed at deterrence may be declared void or excessive.
- Difficulty in Assessing Reasonableness: Especially in long-term or high-stakes commercial contracts.
๐ง 6. Comparative Perspective
Country | Approach |
---|---|
UK | Strict distinction between penalty and liquidated damages; penalties are unenforceable (as per Dunlop v. New Garage and Cavendish v. El Makdessi). |
USA | Similar to India; courts uphold reasonable liquidated damages but reject penalties. |
India | Middle path: Section 74 applies to both, with courts awarding reasonable compensation. |
๐งพ 7. Practical Suggestions for Drafting
- Use clear language and label clause as โgenuine pre-estimateโ.
- Avoid amounts that are disproportionate to the actual contract value.
- Justify the clause with commercial reasoning, e.g., loss of time, profit, reputation.
- Include separate clauses for recoverable losses (if quantifiable).
๐ 8. Conclusion
The law on liquidated damages and penalty clauses in India strikes a balance between freedom of contract and judicial fairness. Courts emphasize reasonableness, commercial intent, and the need to compensate without punishing. While they uphold such clauses when drafted properly, abuse or excessive penalties are not enforceable.
๐ Key Case Laws for Reference
- Fateh Chand v. Balkishan Dass (1963)
- ONGC v. Saw Pipes Ltd. (2003)
- Kailash Nath Associates v. DDA (2015)
- Maula Bux v. Union of India (1970)
Flowchart: Liquidated Damages & Penalty Clauses
Start
|
v
Is there a clause in the contract specifying a sum for breach?
|
+—> NO –> Compensation under Section 73 based on actual loss
|
v
YES
|
v
Is the sum a genuine pre-estimate of loss?
|
+—> YES (Liquidated Damages)
| |
| v
| Reasonable amount may be awarded
| even if actual loss not proven
| |
| [Ref: ONGC v. Saw Pipes Ltd.]
|
+—> NO (Penalty Clause)
|
v
Court will award only
reasonable compensation
(Not the full amount)
|
[Ref: Fateh Chand v. Balkishan Dass]
|
v
Did the breach cause loss or inconvenience?
|
+—> NO –> No compensation (e.g., Kailash Nath v. DDA)
|
v
YES
|
v
Court assesses reasonableness of amount:
- Is it excessive?
- Is it deterrent rather than compensatory?
- Can actual loss be estimated?
|
v
Final Decision:
Court grants reasonable compensation
(not exceeding the stipulated sum)